Crispin School PSBP2
Location
Street
Value
£7m
Completion
Summer 2020
Contractor
Halsall Construction
Futures for Somerset are currently working with Crispin School to deliver a new three storey teaching block.
Futures for Somerset secured funding through the Priority School Building Project 2 Scheme. Futures for Somerset are providing a range of services into this project. Delivering an end-to-end service we have provided Feasibility, Project Management, Procurement and Employer’s Agent Services.
Planning has been submitted in April 2019, which replaces poor condition DT, Art and Food Technology classrooms. The long-awaited project will deliver curriculum spaces fit for the 21st century giving students the opportunity to thrive.
The new block is being delivered in association with Stride Treglown Architects and Halsall Construction Ltd. The new block will be open in June 2020 with the old block being demolished by the end of August 2020.